Hi Jammie
There is a way to get your scheduled number, but it may be worth testing it just to make sure it works for you in your environment.
If you filter the agents and then select <g class="gr_ gr_838 gr-alert gr_gramm gr_inline_cards gr_run_anim Grammar only-ins replaceWithoutSep" id="838" data-gr-id="838">Schedule</g> States and tick the box "Filter Using Following Schedule States", then tick the shifts box, it will only show you agents that are on the shifts listed.
In my test environment, this has filtered it from 299 agents to 135 agents using the count in the top corner. I manually counted the shifts with no filter and it was 135 scheduled agents on actual shifts. So I believe this will work, but as stated, you might want to check it works in your environment.
Other than that, it would be a report from ETL or an export to Excel with a weird and wonderful count formula
thanks
Sam
------------------------------
Samuel Jillard
Senior WFO consultant
Genesys - Employees
------------------------------
Original Message:
Sent: 07-06-2018 07:37
From: Jammie Cross
Subject: Can I filter out day off agents?
Hi Samuel,
Thanks for this information and we already use the start time column in order to get day off at the bottom. However, we have over 700 agents and need to give a headcount each day that will tell how many total we have scheduled. This is why we wanted to filter out day off so we could use the count at the top of the page.
Since this isn't an option, is there another way (without having to build something myself with the ETL database) that will easily show me the total number of agents scheduled for the entire day?
------------------------------
Jammie Cross
BB&T (Branch Banking & Trust Comp.)
Original Message:
Sent: 07-06-2018 05:29
From: Samuel Jillard
Subject: Can I filter out day off agents?
Hi Jammie
You can't filter people out who have a day off, but you can sort by Start Time, by adding the Start Time Column in Actions>Options>Columns.
When sorting by Start time, this will put all agents on a day off or not scheduled at the bottom off the screen, so you will only see them if you scroll all the way down
Thanks
Sam
------------------------------
Samuel Jillard
Senior WFO consultant
Genesys - Employees
Original Message:
Sent: 07-05-2018 13:04
From: Jammie Cross
Subject: Can I filter out day off agents?
Hey everyone!
When looking at the schedule - Master schedule - intraday, is there a way to filter out the agents who are scheduled off this day and instead just show the scheduled agents?