Hi Tracy,
thanks for your feedback.
What I have understood, the secondary activity cannot be used for prioritize specific activity, it just for inform the system if we want schedule the activity or not.
In other words, the system doesn't take in consideration, the fact the activity is configured like secondary and do not priorise primary activity compared to secondary activity when we start the builder?
thanks
jeremy
------------------------------
Jeremy Monzo
------------------------------
Original Message:
Sent: 03-19-2020 14:27
From: Tracy Vickers
Subject: Secondary activity
Hi Jeremy,
There isn't a way to have the Activity Set act as secondary, from my tests if the activity is secondary for the agents and assigned to an activity set it will be scheduled.
If no other people have an idea I would post your idea on the ideas portal - https://pureengage.ideas.aha.io/portal_session/new
------------------------------
Tracy
Genesys
Original Message:
Sent: 03-17-2020 13:18
From: Jeremy Monzo
Subject: Secondary activity
Hello,
I use the latest WFM version on Genesys PureEngage.
I would like use the secondary activity to priorise specific activities on my schedules.
- The activity secondary must be integrated in a activty set to be taken in consideration in the priority or it is not a requirement?
- I can only have 2 levels of priority (primary/secondary) configured on each skill. I cannot use differents skill levels like in the genesys configuration for routing?
- Is there people to share feedback regarding this feature?
thanks
Jeremy
#WorkforceManagement
------------------------------
Jeremy Monzo
------------------------------