Thank you for the additional information Timothy. We will be exploring how this might work and may reach out to you for additional feedback some time in the not too distant future.
Original Message:
Sent: 09-30-2026 06:49
From: Timothy Milburn
Subject: 🎯 New Release: Adjustments for Out of Adherence Exceptions
Thanks for the response and clarification.
I understand your point regarding cancelled meetings or training sessions, and I agree that, in an ideal process, those activities should be removed from the schedule by the relevant person before the event takes place. If this feature did this, or gave the option to do this as part of the approval process that would be great. My concern is less around the process itself and more around how approved adjustments are represented within the schedule once they have been approved.
I also appreciate the clarification that a single adjustment request from 10:00 to 10:45 would cover both sides of my break example. That's helpful and addresses part of the concern.
What I am trying to describe regarding the schedule view is that, from a planning and operational perspective, I often use the schedule to understand what was planned versus what actually happened. If an adjustment has been approved, we have already determined that the difference between schedule and actuals was legitimate.
Using the break example:
Scheduled break: 10:00-10:15
Actual break: 10:30-10:45
Adjustment approved
Once approved, adherence is corrected, but the schedule still shows a break at 10:00-10:15 and queue work at 10:30-10:45, while the actual activity shows the opposite. Technically this is accurate from a historical scheduling perspective, but it still leaves what appears to be a mismatch when reviewing the day.
My thought was that an approved adjustment could optionally be reflected visually within the schedule view, perhaps as an adjusted schedule layer or overlay, so that users can easily distinguish between:
The original planned activity.
The approved adjusted activity.
The actual activity.
This would preserve the audit trail and original schedule while providing a cleaner representation of what was ultimately deemed acceptable by the business.
From my perspective, once an exception has been reviewed and approved, there should be a clear visual indication within the schedule view that the variance has been accepted. Otherwise, the schedule continues to show a discrepancy between planned and actual activity, despite the business having already determined that the variance was legitimate.
At the moment, the feature feels primarily designed as an adherence-calculation adjustment tool. I had initially expected it to help explain and reconcile the differences between schedule and actual activity when reviewing an agent's day. An approved-adjustment overlay or similar visual representation would, in my view, make the feature significantly more valuable from an operational and planning perspective. Unfortunately, in the way it currently works we will continue to ask Agents to have their exceptions manually verified by their Team Manager who will in turn send this to planning by email to manually update the schedules. For legitimate exceptions the schedule activity would then accurately reflect the actual activity.
------------------------------
Timothy
Global Workforce Planning Manager
------------------------------
Original Message:
Sent: 09-29-2026 14:09
From: Belinda Herrera
Subject: 🎯 New Release: Adjustments for Out of Adherence Exceptions
Hi Timothy,
Glad you've had a chance to test this new feature and really appreciate the feedback.
If an agent is scheduled for a meeting or training and it gets canceled the expectation would be that whoever they had the meeting or training scheduled with (Trainer, Supervisor, etc) would make sure to remove that activity code from their schedule. Certainly the agent could submit an adherence adjustment request but likely the better option would be to have the activity code removed from their schedule.
For your second example where an agent takes their break later than scheduled, they could submit one adjustment request that would cover the entire time period and would take care of both the 15 minutes where they were scheduled to take their break but were On Queue and the 15 minutes after their scheduled break time where they were scheduled to be On Queue but were on break. In your specific example, an adjustment for 10:00 to 10:45 could be submitted and would take care of adjusting their adherence on both ends.
Your comment about how "moving the scheduled break activity to the actual time taken would maintain a much cleaner view of scheduled versus actual activity". Would you mind elaborating on that a little? My thought is that keeping the break where it was originally scheduled would actually provide you a better view of scheduled vs. actual activity because moving the break to where it was actually taken would then show that the scheduled and actual were the same. Maybe I'm not understanding where or how you would like to see this comparison so any additional information you can share is greatly appreciated.
Again, thank you for taking the time to test it and provide valuable feedback. We will be reviewing all feedback and facilitating additional interviews with customers to further enhance this feature to make sure it's as valuable to you as it can be.
------------------------------
Belinda Herrera
Genesys, Staff Product Manager
------------------------------
Original Message:
Sent: 09-25-2026 06:12
From: Timothy Milburn
Subject: 🎯 New Release: Adjustments for Out of Adherence Exceptions
We have tested this functionality and, unless we are misunderstanding how it is intended to work, the way it operates can make the comparison between scheduled and actual activities look very messy.
For example, if an agent has an hour of training or a meeting scheduled and, for any reason, that activity does not take place, the agent can submit an exception to exclude it from adherence calculations. If the exception is approved, the activity is ignored for adherence purposes, but the original scheduled activity remains on the schedule even though it never actually happened.
Similarly, if a break or lunch is taken later than scheduled, such as a break planned for 10:00 to 10:15 but legitimately taken at 10:30 to 10:45 due to queue demand, the agent can submit an exception to exclude the non-adherence during the actual break time. However, the original scheduled break at 10:00 to 10:15 remains unchanged, meaning a second exception is also required to exclude the non-adherence during the originally scheduled period.
My expectation would be that, once approved, the system could simply move the scheduled break activity to the actual time taken. This would maintain a much cleaner view of scheduled versus actual activity while still allowing managers to decide whether the exception is valid or whether the agent simply chose to take their break at the wrong time.
In its current form, we are unlikely to use this functionality, as the drawbacks outweigh the benefits. It feels like this could have been a really positive enhancement, but at present it creates more complexity than value. Of course, it is entirely possible that we are misunderstanding the intended use case or purpose of the feature.
------------------------------
Timothy
Global Workforce Planning Manager
------------------------------