As far as I know the best way to get what you're trying to do is to have fixed breaks so it'll be
On Queue as the base then add WFH on top but rather than spanning across the entire day like you have, add it in multiple instances so it does not overlap with breaks.
This will mean you lose the ability to have the flexibility of breaks unfortunately.
https://genesyscloud.ideas.aha.io/ideas/WEM-I-193
Here's a post from idea portal which you can vote on where it's about changing ability to change default activity from on queue to a custom value.
------------------------------
Brahdilleone Dermody
na
------------------------------
Original Message:
Sent: 01-08-2026 12:54
From: Julie Kleedorfer
Subject: Work plan with an added On Queue activity code - getting error
I created an activity code for agents working at home. It's an On Queue code labeled WFH. When i try to use it on a work plan it won't allow me because of over lapping with the breaks and lunches. Am I doing something wrong or is this just how Genesys works?


Activities 'Meal' and 'WFH' in daily shift 'Shift 1' will overlap. Move one of them to a different time
'Shift 1' paid time of 8 hour(s) cannot be less than activity paid time of 9 hour(s) 30 minute(s)
This work plan cannot produce any valid schedules due to constraint conflicts. Please adjust some constraints and re-validate
#WFMConfiguration,BestPractices
------------------------------
Julie Kleedorfer
Administrative Assistant
------------------------------