Dan,
The possible route paths appear that have historical data for the route for 6 weeks, i.e. Queue / Language / Skill. Adding the route path manually will work prior to having the data collection. The agents that are able to work against those route paths will appear in the Agent tab (list) for routes of the Planning Group. See important note about planning groups / route paths below, which is documented in the Planning Group configuration screens. Auditing for the proper agent targets is an important step in finalizing updates to a planning group as it impacts agents scheduled against the forecast workload from the planning group route path configurations.
- Note: Agents must be able to handle all of the route paths in this planning group to be scheduled against any of the route paths in this Planning Group.
If this is a new skill ALL agents are assigned/able to handle in a PG, and there is no need to forecast separately for it, adding it to an existing Planning Group is recommended.
After adding the route to the Planning Group, the GC WFM forecast will forecast for the new workload with the
next forecast generation. Make your Planning Group configuration updates prior to your next forecasting/scheduling exercises.
Let us know how it goes, or follow up questions.
------------------------------
Chuck Swain
Genesys
WEM Leadership
------------------------------