I do! Use the conditional rules. For example, for Independence day in the US you will need 3 Holidays set up.
1st, Set up a recurring every year for the 4th day of July, then add the conditional rules and select Mo, Tu, We, Th Fr as the days
2nd, Set up a recurring every year for the 3rd day of July, then add the conditional rule and select on Fr as the only day
3rd, Set up a recurring every year for the 5th day of July, then add the conditional rule and select Mo as the only day
------------------------------
Mike Steinke
Inflow Communications
------------------------------
Original Message:
Sent: 09-17-2020 16:36
From: Brenda Wynne
Subject: Holiday Scheduling
I haven't even figured out how to make a recurring holiday work if the holiday is observed on the preceding Friday for Saturday holidays, or if the following Monday is observed for Sunday holidays. We have to watch / monitor numerous holidays and make manual adjustments.
Anyone have any tips for this?
------------------------------
Brenda Wynne
Alcon Vision LLC
Original Message:
Sent: 11-13-2019 13:04
From: Ben Marthin
Subject: Holiday Scheduling
We have 6 Schedule Groups and each group all observe the same holiday schedule.
As it is right now, I have to enter the individual holidays into each group as that is the only way I know how to do this. Is it possible to put all the holidays in one container and then have the 6 Schedule Groups use the container with all the holidays?