Hi Heather,
For activities within work plan configuration even though the step-value of the control is 15m you can override the numeric value. I do see that in activity codes (e.g., say you created a '10m Break' activity code with the default activity category of Break) that it does not allow a similar override. We will get a fix out to resolve the activity code configuration issue.